Factory in Szczecin - ST³ Offshore

Factory in Szczecin

Production Hall TPs:
- Length: 240 m
- width: 45 m
- height 31 m
- gate: 20 x 35 (width)
Production Hall Jackets:
- length: 240 m
- width: 40 m
- height: 42 m (as 14-storey skyscraper)
- gate: 31 x 35 (width)
Painting hall:
- area: 3480 m2
- length: 120 m
- width: 29 m
- height: 31 m
Brdowski Bridge:
- length: 197, 2 m
- road length: 247,95 m (land)
- road length:120,44 m (island)
- road width: 2 x 3,0 m
- project realization: 2013 - 2015
Gantry Crane
- lifting capacity: 1400 t
- height: 120 m (the highest crane in Europe)
- hook height: 95 m
- total weight of crane: approx.1800 t
- span between the legs of crane: 48 m
- speed of crane: 0,67 m/s
- the hoisting speed is 6m/sec
- total rope lengths: 2 km
- 8 - number of parts in which gantry crane arrived in Szczecin
- 80-340 t - the weight of individual components of crane
Gantry Crane Area
- length: 245 m
- crane area: 11,400 m2
- distance between the rails: 48,3 m
Pier:
- length of the water part: 145 m
- width of the water part between the rubbing strakes: 43,4 m
- depth of water area: 6,50 m
- span of the gantry crane rails: 48,32 m
- area of water: 6380 m²
- length of beams in the land part: 245 m
- total length of gantry crane rail: 392 m
Mazowieckie Quay:
- length: 200 m
- depth: 9 m
- max. load on site: 20 kN/m2

ST³ Offshore production site was put into operation at the end of 2015. It was designed as a serial production factory of large-scale steel foundations. It is the first factory in Europe, where the steel structures are being produced constantly (during 3-shifts work schedule).
The construction site is located on the Ostrów Brdowski island, in the north part of Szczecin, 2 km from the city center. It covers an area of 220 000 m2. Around 100 000 m² is the fabrication area, the rest left as storage field for completed foundations. The storage capacity is approx. 50% of an annual production.


STORY OF THE FACILITY

  • June 2013 – building permit received from West Pomeranian Voivode
  • Oct.  2013 – joining the facility’s area to the Special Economic Zone “Euro-Park Mielec”
  • 5.12.2013 – ground-breaking ceremony. Official start of factory building
  • Dec. 2014 – Finishing of main hall steel construction
  • Feb. 2015 – Finishing of painting hall steel construction
  • 1 Quarter 2015 – montage of the production machines in the main hall
  • 6.2015 – beginning of  pier construction ( land part)
  • 10.2015 – delivery of all gantry crane components
  • 4 Quarter 2015 –facility receives permission of use from the West Pomeranian Construction Site Inspector
  • Apr. 2016 – permission of use of gantry crane
  • 2 Quarter 2016 – permission of use the pier (land and water part)

 

 

Gantry crane assembly